Ballari Road elevated corridor construction will not completely shut down the road for 18 months
BDA clarified that the construction of the four-lane elevated corridor on Ballari Road, from the UAS bus stand to Mekhri Circle, will not completely shut down the road for 18 months. The elevated corridor is planned at a cost of ₹445.7 crore, involving 49 pillars and a 1.74 km length. The construction will allow vehicle movement through controlled traffic restrictions and phased route changes, ensuring continuous flow. The elevated corridor will feature a rotary junction at Mekhri Circle, with down ramps planned for C.V. Raman Road towards Yeshwanthpur and Jayamahal Road.